- Bottle storage, bottling hall and outdoor area (D-799, D-804)
- Fibrofor HIGH GRADE 19 mm
- 2.300 m² (inside) + 500 m² (outside)
- Bavaria (D-82)
- Concrete core activation
In this construction project, the statically chargeable plastic microfibre HIGH GRADE 19 was installed with few joints, with fields of 36 x 24 m each and additional reinforcement. XPS insulation was used at the edges. The outer surface was executed with cut joints and a required crack width of 0.2 mm.
Advantages:
- Reinforcement construction is not necessary or is reduced (cost and time savings)
- Structural design according to Eurocode 2
- All types of surface treatments possible
- Surfaces with few joints up to 1.000 m²
- No corrosion
- Resistant to salt water and aggressive liquids